The FY2025 single audit reports 1 finding: 1 significant deficiency. Audits on file for FY2023–FY2025: FY2023, FY2024, FY2025.

Score: 3 of 100 (FY2025 audit)

The sum of eight parts, each read from the audit. How the score works.

PartRulePointsMax
Material weaknesses8 points each024
Significant deficiencies3 points each39
Repeat findings5 points each015
Longest repeat chain2 years 3, 3 years 6, 4 years 9, 5+ years 12012
Modified major-program opinionsqualified 8 each; any adverse or disclaimer 15015
Questioned costsknown amount of $25,000 or more, by share and dollars015
Going concernauditor included a going-concern paragraph05
Prior-year latenessprior-year audit late or not filed, scored only with a finding05
Score3100

Federal funding, FY2025

$2,535,540 in federal awards spent, across 8 programs. Largest funding agencies:

AgencySpent
Department of Education$2,328,442
Department of Agriculture$207,098

FY2025 audit

FAC record
2025-06-GSAFAC-0000391964
Fiscal year end
June 30, 2025
Accepted by FAC
January 13, 2026
Federal spending
$2,535,540 · 8 programs
Major programs
1
Score
3 of 100

Finding 2025-001

significant deficiencyother matters

Program
SPECIAL EDUCATION CLUSTER (IDEA) (84.027)
Compliance requirement
Procurement and suspension and debarment
FAC record
FY2025 audit on fac.gov
Finding text from the filing

Type of Findings: Significant Deficiency in Internal Control over Compliance, Other Matters

Criteria or Specific Requirement: Per 2 CFR 200.303, requires that non-federal entities receiving federal awards establish and maintain internal control designed to reasonably ensure compliance with federal statutes, regulations, and the terms and conditions of the federal award. Effective internal controls should include procedures in place to ensure the required certifications for covered contracts and subawards are received, documented, and contracts are not made with a debarred or suspended party.

Condition: During our review we noted that the district followed procurement guidelines and policies established in the DJB Federal Procurement guide, but the District does not have an established suspension and debarment policy that they follow. Effective internal controls should include procedures in place to ensure the required certifications for covered contracts and subawards are received, documented, and contracts are not made with a debarred or suspended party.

Questioned costs: None

Context: The sole vendor engaged under the IDEA grant was found to have no evidence of verification that the vendor was not suspended or debarred by the District. We did later verify that the vendor was not suspended or debarred per verification on SAM.gov.

Cause: The District engaged with the vendor in a contract effective from 07/01/2023, but did not conduct a suspension and debarment check prior to engagement.

Effect: The District could not be in compliance with suspension and debarment requirements for its federal programs.

Repeat Finding: No

Recommendation: We recommend that the District implement policies for verifying suspension and debarment compliance for all transactions with vendors that are paid with Federal Funds.

View of Responsible Officials: There is no disagreement with the audit finding.

Corrective action plan - management response: The District will formally adopt a Suspension and Debarment Verification Procedure that outlines the required process for verifying all vendors and subrecipients before entering into any contract funded by federal awards.

Staff will verify suspension and debarment status by checking the System for Award Management (SAM.gov) prior to contract execution and will maintain documentation of verification in the procurement file.

The Business Services Department will complete training on the new procedure and documentation requirements.

Responsible Party: Business Manager

Completion Date: Procedure adoption and staff training by December 31, 2025

FY2024 audit

FAC record
2024-06-GSAFAC-0000344144
Fiscal year end
June 30, 2024
Accepted by FAC
December 19, 2024
Federal spending
$1,818,253 · 6 programs
Major programs
1
Score
0 of 100

No findings reported.

FY2023 audit

FAC record
2023-06-GSAFAC-0000017005
Fiscal year end
June 30, 2023
Accepted by FAC
January 16, 2024
Federal spending
$1,284,607 · 6 programs
Major programs
1
Score
0 of 100

No findings reported.