The FY2025 single audit reports no findings. Audits on file for FY2023–FY2025: FY2023, FY2024, FY2025.

Score: 0 of 100 (FY2025 audit)

The sum of eight parts, each read from the audit. How the score works.

PartRulePointsMax
Material weaknesses8 points each024
Significant deficiencies3 points each09
Repeat findings5 points each015
Longest repeat chain2 years 3, 3 years 6, 4 years 9, 5+ years 12012
Modified major-program opinionsqualified 8 each; any adverse or disclaimer 15015
Questioned costsknown amount of $25,000 or more, by share and dollars015
Going concernauditor included a going-concern paragraph05
Prior-year latenessprior-year audit late or not filed, scored only with a finding05
Score0100

Federal funding, FY2025

$2,211,340 in federal awards spent, across 5 programs. Largest funding agencies:

AgencySpent
Department of Transportation$1,326,080
Department of Housing and Urban Development$752,915
Department of the Treasury$104,661

FY2025 audit

FAC record
2025-09-GSAFAC-0000420940
Fiscal year end
September 30, 2025
Accepted by FAC
June 16, 2026
Federal spending
$2,211,340 · 5 programs
Major programs
1
Score
0 of 100

No findings reported.

FY2024 audit

FAC record
2024-09-GSAFAC-0000375991
Fiscal year end
September 30, 2024
Accepted by FAC
July 28, 2025
Federal spending
$2,945,611 · 7 programs
Major programs
2
Score
0 of 100

Finding 2024-001

other matters

Program
CORONAVIRUS STATE AND LOCAL FISCAL RECOVERY FUNDS (21.027)
Compliance requirement
Reporting
FAC record
FY2024 audit on fac.gov
Finding text from the filing

Finding 2024-001: Timely submission for Annual Program & Expenditure Report Major Program: ARP Act Federal Agency: U.S. Department of Treasury Assistant Listing Number: 21.027 Criteria: Metropolitan cities and counties with a population below 250,000 residents that are allocated less than $10 million in Coronavirus State and Local Fiscal Recovery Funds (SLFRF) funding, are required to submit annual Project and Expenditure Reports to the Department of Treasury. This report is due annually, by April 30th each year. Condition: There was turnover in the finance department in 2023 and 2024 of both the Grant position and Director of Finance position. Cause: Because of the turnover in key positions in the finance department, the previous Director of Finance was not aware of the reporting deadline. Effect: The Project & Expenditure Report was submitted on May 9, 2024, which was after the submission deadline. Repeat Finding: No Recommendation: The Director of Finance should submit the required Project & Expenditure Report on by the required due date. View of Responsible Officials: See corrective action plan.

FY2023 audit

FAC record
2023-09-GSAFAC-0000045792
Fiscal year end
September 30, 2023
Accepted by FAC
June 27, 2024
Federal spending
$3,354,028 · 8 programs
Major programs
1
Score
0 of 100

No findings reported.