The FY2024 single audit reports 3 findings: 2 significant deficiencies, 2 repeat. Audits on file for FY2023–FY2025: FY2023, FY2024.

No FY2025 single audit on file as of October 30, 2026. For the fiscal year ending September 30, 2025, it was due June 30, 2026, 122 days earlier. It is expected because the FY2024 audit reported $1,232,431 in federal spending; an organization whose federal spending fell below the threshold would not need one.

Score: 42 of 100 (FY2024 audit)

The sum of eight parts, each read from the audit. How the score works.

PartRulePointsMax
Material weaknesses8 points each024
Significant deficiencies3 points each69
Repeat findings5 points each1015
Longest repeat chain2 years 3, 3 years 6, 4 years 9, 5+ years 12612
Modified major-program opinionsqualified 8 each; any adverse or disclaimer 151515
Questioned costsknown amount of $25,000 or more, by share and dollars015
Going concernauditor included a going-concern paragraph05
Prior-year latenessprior-year audit late or not filed, scored only with a finding55
Score42100

Federal funding, FY2024

$1,232,431 in federal awards spent, across 4 programs. Largest funding agencies:

AgencySpent
Environmental Protection Agency$880,123
Department of the Treasury$209,909
Department of Homeland Security$85,849

FY2024 audit

FAC record
2024-09-GSAFAC-0000406308
Fiscal year end
September 30, 2024
Accepted by FAC
March 6, 2026; submitted 249 days after its due date (June 30, 2025)
Federal spending
$1,232,431 · 4 programs
Major programs
2; adverse opinion or disclaimer on 2
Score
42 of 100

Finding 2024-001

significant deficiencyrepeat finding

Program
DRINKING WATER STATE REVOLVING FUND CLUSTER (66.468)
Compliance requirement
Reporting
Repeat
Chain of at least 2 audit years; prior finding 2023-001
FAC record
FY2024 audit on fac.gov
Finding text from the filing

Criteria: Management is responsible for establishing and maintaining effective internal controls over financial reporting. Federal regulations and the City’s internal policies require that all expenses be supported by original invoices and adequate documentation to ensure transactions are recorded accurately, timely, and in the proper reporting period, thereby providing reliable financial data

Condition: The City has not performed complete reconciliations for key balance sheet accounts, including cash, accounts receivable, fixed assets, debt, deferred revenues, other accrued liabilities, and net position, resulting in material audit adjustments. In addition, we identified instances where invoices and supporting documentation for certain expenses were missing or incomplete. Automatic payments and deposits were not recorded, and other entries required reclassification to correct the balances.

Effect: The absence of regular and thorough reconciliations, as well as missing invoices and supporting documentation, increases the risk of misstatements, undetected errors, and misleading financial information that could impair management’s decision-making.

Cause: There was a lack of staff training and a failure to prioritize financial reporting, reconciliations of critical balance sheet accounts, and the retention of supporting documentation for expense transactions.

Recommendation: We recommend that finance personnel reconcile all balance sheet accounts for accuracy and maintain supporting documentation for all expenses. Procedures should be implemented to ensure that all invoices and supporting documents are retained and reviewed prior to payment and that all balance sheet accounts are reconciled to the general ledger on a timely basis

Views of responsible official and planned corrective actions: The City has implemented additional procedures to ensure all balance sheet accounts are being reconciled in a timely basis. Additional training and supervision will be provided to the appropriate personnel. The City will also strengthen its documentation retention policies to ensure all expenses are properly supported.

Finding 2024-002

significant deficiencyrepeat finding

Program
DRINKING WATER STATE REVOLVING FUND CLUSTER (66.468)
Compliance requirement
Reporting
Repeat
Chain of 3 audit years; prior finding 2023-002
FAC record
FY2024 audit on fac.gov
Finding text from the filing

Criteria: In accordance with federal regulations (Uniform Guidance 2 CFR 200), recipients of federal awards are required to submit their single audit within the stipulated timeframe, usually nine months after the end of the fiscal year.

Condition: During the 2024 audit, it was identified that the City failed to submit its single audit report for the fiscal year ending September 30, 2024 within the required timeframe, which is a violation of the Uniform Guidance requirements.

Effect: The late submission of the single audit report has resulted in a breach of compliance with federal regulations. This non-compliance has the potential to disallow funding from federal agencies.

Cause: The delay in submitting the single audit report was primarily attributed to a change in finance personnel.

Recommendation: We recommend the City develop a system of monitoring grant requirements and establish a timeline for meeting deadlines related to reporting in compliance with the Uniform Guidance.

Views of responsible official and planned corrective actions: The City will prepare for financial statement audits to ensure audits are completed timely.

Finding 2024-003

other findings

Program
CORONAVIRUS STATE AND LOCAL FISCAL RECOVERY FUNDS (21.027)
Compliance requirement
Reporting
FAC record
FY2024 audit on fac.gov
Finding text from the filing

Criteria: In accordance with federal regulation (Uniform Guidance 2 CFR 200.328 and CFR 35.4(c), recipients of federal awards are required to submit a Project and Expenditure Report on a quarterly or annually basis as specified in the SLFRF Compliance and Reporting Guidance.

Condition: During the 2024 audit the City did not file the required Project and Expenditure Report for the period ending September 30, 2024, within the required timeframe, which is a violation of the Uniform Guidance requirements.

Effect: Failure to submit the required report may result in the withholding of federal funds, increased oversight, or other administrative actions by the U.S. Department of the Treasury. It also impairs transparency and accountability for the use of federal funds

Cause: The delay in submitting the expenditure report was primarily attributed to a change in finance personnel.

Recommendation: We recommend that the City develop a system of monitoring grant requirements and establish a timeline for meeting deadlines related to reporting in compliance with the Uniform Guidance.

Views of responsible official and planned corrective actions: The City will file the required closeout project and expenditure report immediately, and staff will receive training in reporting requirements to ensure timely submissions in the future.

FY2023 audit

FAC record
2023-09-GSAFAC-0000069649
Fiscal year end
September 30, 2023
Accepted by FAC
December 9, 2024; submitted 162 days after its due date (June 30, 2024)
Federal spending
$1,259,436 · 2 programs
Major programs
1
Score
16 of 100

Finding 2023-002

significant deficiencyrepeat finding

Program
DRINKING WATER STATE REVOLVING FUND (66.468)
Compliance requirement
Other
Repeat
Chain of 2 audit years; prior finding 2022-001
FAC record
FY2023 audit on fac.gov
Finding text from the filing

Criteria: In accordance with federal regulations (Uniform Guidance 2 CFR 200), recipients of federal awards are required to submit their single audit within the stipulated timeframe, usually nine months after the end of the fiscal year.

Condition: During the 2023 audit, it was identified that the City failed to submit its single audit report for the fiscal year ending September 30, 2023 within the required timeframe, which is a violation of the Uniform Guidance requirements.

Effect: The late submission of the single audit report has resulted in a breach of compliance with federal regulations. This non-compliance has the potential to disallow funding from federal agencies.

Cause: The delay in submitting the single audit report was primarily attributed to a change in finance personnel.

Recommendation: We recommend the City develop a system of monitoring grant requirements and establish a timeline for meeting deadlines related to reporting in compliance with the Uniform Guidance.