Finding 2024-003
significant deficiency
- Program
- CDBG - ENTITLEMENT GRANTS CLUSTER (14.218)
- Compliance requirement
- Reporting
- FAC record
- FY2024 audit on fac.gov
Finding text from the filing
Reporting – FFATA Subawards
Federal Agency: U.S. Department of Housing and Urban Development Federal Program Name: Community Development Block Grants/Entitlement Grants Assistance Listing Number: 14.218 Award Number and Period: B-23-UC-48-0500, B-22-UC-48-0500 October 1, 2023–September 1, 2030, October 1, 2022–September 1, 2029 Pass-Through Agency: N/A Pass-Through Number(s): N/A Type of Finding: Significant Deficiency in Internal Control over Compliance and Noncompliance
Criteria or specific requirement: Per 2 CFR 200.303(a), Bexar County (The County) must establish and maintain effective internal control over the Federal award that provides reasonable assurance that it is managing the federal award in compliance with federal statutes, regulations, and the terms and conditions of the federal award. These internal controls should be in compliance with guidance in the “Internal Control Integrated Framework” issued by the Committee of Sponsoring Organizations of the Treadway Commission (COSO).
Under the requirements of the Federal Funding Accountability and Transparency Act (FFATA) (Pub. L. No. 109- 282), as amended by Section 6202 of Public Law 110-252, recipients (i.e., direct recipients) of grants or cooperative agreements are required to report first-tier subawards of $30,000 or more to the Federal Funding Accountability and Transparency Act Subaward Reporting System (FSRS) no later than the last day of the month following the month in which the subaward/subaward amendment obligation was made or the subcontract award/subcontract modification was made.
Condition: The County’s Auditors Office (CAO) is responsible for submitting all required subawards in the Federal Funding Accountability and Transparency Act Subaward Reporting System (FSRS). A standard FFATA Reporting form has been created by the CAO that includes all required elements to be submitted. Program departments must complete and submit the form to the Grant Accountant in the CAO for all federal subawards with amounts over $30,000 as soon as the subaward contract is approved by the Commissioner’s Court so that it can be included in the next month’s submission.
During our testing, we noted the following compliance exceptions:
Transactions Tested Subawards not reported Report not timely Subaward amount incorrect Subaward missing key elements 4 0 4 0 0 Dollar Amount of Tested Transactions Subawards not reported Report not timely Subaward amount incorrect Subaward missing key elements $1,102,564 $0 $1,102,564 $0 $0
Questioned costs: None.
Context: See “Condition.”
Cause: The delays were attributed to miscommunication between the Grant Accountant and the Program Department, as well as the Program Department not informing the Grant Accountant promptly when the subawards were approved in Commissioner’s Court.
Effect: Failure to provide documentation of timely submission of subawards in FSRS will result in noncompliance with the federal grant guidelines.
Repeat Finding: No.
Recommendation: The County should enhance existing controls around the submission of required subawards in FSRS to ensure they are reported timely.
Views of responsible officials: See corrective action plan.