The FY2025 single audit reports 1 finding: 1 significant deficiency.

Score: 3 of 100 (FY2025 audit)

The sum of eight parts, each read from the audit. How the score works.

PartRulePointsMax
Material weaknesses8 points each024
Significant deficiencies3 points each39
Repeat findings5 points each015
Longest repeat chain2 years 3, 3 years 6, 4 years 9, 5+ years 12012
Modified major-program opinionsqualified 8 each; any adverse or disclaimer 15015
Questioned costsknown amount of $25,000 or more, by share and dollars015
Going concernauditor included a going-concern paragraph05
Prior-year latenessprior-year audit late or not filed, scored only with a finding05
Score3100

Federal funding, FY2025

$1,657,241 in federal awards spent, across 1 program. Largest funding agencies:

AgencySpent
Department of the Treasury$1,657,241

FY2025 audit

FAC record
2025-12-GSAFAC-0000420499
Fiscal year end
December 31, 2025
Accepted by FAC
June 10, 2026
Federal spending
$1,657,241 · 1 program
Major programs
1
Score
3 of 100

Finding 2025-001

significant deficiencyother matters

Program
CORONAVIRUS STATE AND LOCAL FISCAL RECOVERY FUNDS (21.027)
Compliance requirement
Procurement and suspension and debarment
FAC record
FY2025 audit on fac.gov
Finding text from the filing

Criteria:

NAMI Greater San Antonio, Inc. (the “Organization”) and Bexar County had an agreement dated September 4, 2024. Section 4.04 of the agreement stated the Organization must comply with 2 CFR Part 200 Subpart D, Procurement when expending federal funds.

Condition:

During the audit, it was noted the Organization did not have a procurement process in place as required by the procurement standards set forth in 2 CFR Part 200 Subpart D for subcontractors.

Cause:

The Organization had not received funding in the previous years that adhered to strict compliance requirements as outlined in 2 CFR Part 200. Management is aware of the compliance requirement set forth in 2 CFR Part 200 and has implemented internal controls to comply with compliance requirements.

Effect or potential effect:

The Organization is not in compliance with the Subrecipient Obligations clause of the agreement and within the procurement standards set forth in 2 CFR Part 200 Subpart D.