The FY2025 single audit reports 1 finding: 1 material weakness. Audits on file for FY2023–FY2025: FY2023, FY2024, FY2025.

Score: 16 of 100 (FY2025 audit)

The sum of eight parts, each read from the audit. How the score works.

PartRulePointsMax
Material weaknesses8 points each824
Significant deficiencies3 points each09
Repeat findings5 points each015
Longest repeat chain2 years 3, 3 years 6, 4 years 9, 5+ years 12012
Modified major-program opinionsqualified 8 each; any adverse or disclaimer 15815
Questioned costsknown amount of $25,000 or more, by share and dollars015
Going concernauditor included a going-concern paragraph05
Prior-year latenessprior-year audit late or not filed, scored only with a finding05
Score16100

Federal funding, FY2025

$3,473,042 in federal awards spent, across 28 programs. Largest funding agencies:

AgencySpent
Department of Health and Human Services$2,528,313
Department of Agriculture$407,672
Department of Homeland Security$266,992

FY2025 audit

FAC record
2025-12-GSAFAC-0000430289
Fiscal year end
December 31, 2025
Accepted by FAC
September 30, 2026
Federal spending
$3,473,042 · 28 programs
Major programs
5; qualified opinion on 1
Score
16 of 100

Finding 2025-004

material weaknessother matters

Program
FOREST SERVICE SCHOOLS AND ROADS CLUSTER (10.665)
Compliance requirement
Activities allowed or unallowed; Allowable costs/cost principles
FAC record
FY2025 audit on fac.gov
Finding text from the filing

Finding 2025-004: Schools and Roads Cluster, Assistance Listing No. 10.665, U.S. Department of Agriculture Compliance Requirement: Activities Allowed and Unallowed, Allowable Costs/Cost Principles Grant No.: Not applicable Type of Finding: Internal Control (material weakness) and Compliance (material noncompliance) Criteria: Under 16 USC 500, Schools and Roads funds are required to be used for the benefit of public roads and schools of the county in which the national forest is situated. Accordingly, the County is responsible for ensuring that approved distributions of Schools and Roads funds are transferred and used in accordance with the approved allocation and applicable federal requirements. Condition: The County approved a distribution of $42,764 to the Road and Bridge Fund. However, only $26,893 was transferred to the Road and Bridge Fund. Cause: The County did not have effective internal controls in place to ensure the approved distributions of Schools and Roads funds were completely and accurately transferred to the Road and Bridge Fund. Effect: The Road and Bridge Fund did not receive the full approved distribution of Schools and Roads funds resulting in $15,871 remaining in the General Fund rather than being transferred as approved. An audit adjustment was posted to record a due to/due from between the General Fund and the Road and Bridge Fund as of December 31, 2025. Questioned Costs: None Recommendation: The County should continue to strengthen its internal controls over the review, approval, and transfer of Schools and Roads funds to ensure that approved distributions are complete, accurate, and consistent with approved distribution amounts.

FY2024 audit

FAC record
2024-12-GSAFAC-0000382009
Fiscal year end
December 31, 2024
Accepted by FAC
September 30, 2025
Federal spending
$4,542,973 · 29 programs
Major programs
4
Score
0 of 100

No findings reported.

FY2023 audit

FAC record
2023-12-GSAFAC-0000055004
Fiscal year end
December 31, 2023
Accepted by FAC
September 27, 2024
Federal spending
$6,451,606 · 23 programs
Major programs
2
Score
0 of 100

No findings reported.